Ground floor :

Soldiers learning hall                    4,300  ft2       1,695,000  NIS

Soldiers learning hall yard          3,660 ft2            110,000  NIS

Main Prayer Hall Floor :

Main prayer hall                                       3,800 ft2       1,100,000  NIS

Study hall and Library                             650 ft2            300,000 NIS

Lobby and Memorial Hall                       1,300 ft      550,000 NIS

Sukkah and soldier’s gathering area    1,600 ft2           70,000 NIS

Top floor :

Women’s gallery and lobby                    2,600 ft2           900,000 NIS

Disabled and strollers ramp                   1,300 ft      80,000 NIS

Total construction costs        4,805,000  NIS

Furnishings and facilities inside

Ground floor:

Chairs and tables for 300 soldiers                                110,000 NIS

Multimedia system for soldier’s presentations         65,000 NIS

Kitchen with refrigerators and stainless steel sinks  45,000 NIS

Office with a table, chairs, cabinets, shelves and a computer    12,000 NIS

Main Prayer Hall Floor :

Furniture including seats and a Bimah                         150,000 NIS

Aron Kodesh                                                                       Donated

Top floor :

Seats and Mechitzah                                   90,000  NIS

Total costs for furnishings and facilities  –   472,000  NIS

Schedules :

Frame construction                   5  Months         ( cost  1,500,000 NIS  )

Stone finishing for entire building                    2  Months         ( cost  400,000 NIS  )

Interior work including :

Flooring, Mortar, Electricity, Plumbing,  Aluminum,  Air conditioning, Low voltage, Amplification and Multimedia, Carpentry, Communication, Gypsum Etc…

                                                                             7 Months           (   cost  2,910,000  NIS  )

Funds paid  :

Design and blueprints:  220,000  NIS

Measures  : 9,000  NIS

Soil Testing  :  5,000  NIS

Excavation  :  485,000  NIS

Fence around the court  :  45,000  NIS                          Total paid : ( 2,184,000  NIS )

The Holy Ark  : 150,000 NIS

Building permit  :  10,000  NIS

Frame construction : 1,410,000

Future budgets :

Community members :  100,000  NIS

Temporary synagogue’s sale : 300,000 NIS

Donor commitments :  120,000  NIS

Ministry of Religious Affairs  :  400,000  NIS

Total future budgets ( not including the Ark )  :  920,000  NIS

Construction funds shortage:                                                                                                        3,885,000 NIS

Furniture and Accessories  funds shortage:                        472,000 NIS